PTP 800 Series User Guide Grounding and lightning protection
phn-2513_004v000 (Oct 2012)
2-17
Protection requirements for the IRFU
Applies to IRFU deployments only.
Ensure that all IRFU installations meet the following requirements:
The CMU and IRFU are grounded at their chassis bonding points to the building
grounding system (Figure 48).
The waveguide and antenna are grounded according to their manufacturers
instructions.
Figure 48 Grounding requirements for the IRFU and CMU