Preparing network connections (1+0 and 2+0 links) Chapter 5: Installation
5-84
phn-2513_004v000 (Oct 2012)
Preparing network connections (1+0 and 2+0 links)
This section describes how to prepare the cables to connect the CMU to router ports,
switch ports or other equipment in the customer and (optionally) management networks. It
applies only to unprotected ends (1+0 and 2+0 links).
When installing a 2+0 link, prepare separate network connections for the link ‘A’ and the
link ‘B’ CMUs.
The CMU is not normally connected to the network equipment until antenna alignment is
complete (as described in Task 15: Connecting link to the network on page 6-114).
For all management modes (out-of-band and in-band), decide whether the data network
connection is to be copper or fiber, then perform either Installing a copper data interface
on page 5-85 or Installing a fiber data interface on page 5-86.
For out-of-band management modes (but not in-band), perform Installing a management
interface on page 5-87.